Crew GO/NO-GO Weather Calls Explained

How a foreman decides whether the crew works, adjusts or stands down, and the free tool that does the math for any US jobsite. Written by Errol Kerr, a Truckee excavation foreman.

Short version. Pick limits for wind, rain, lightning, heat, cold and snow before the day starts. If every reading is inside the limits, it is GO. If something is close, it is CAUTION. NO-GO is saved for weather that truly stops the work, so when it shows, people pay attention. The free Crew Weather tool does this for any ZIP code and shows the call for each day of the 16-day forecast.

What the three calls mean

CallWhat it means on site
GOAll readings are inside the crew's limits. Work as planned.
CAUTIONA reading is past one of the crew's limits, or several are. Re-sequence the day, shorten exposure, move the risky task earlier or later.
NO-GOReal stop-work weather in the work day. The affected work stops or moves to another day.

The limits a foreman actually watches

Starting limits for a mountain jobsite

The Crew Weather tool picks a preset by climate zone, then every number can be changed. The mountain preset, which fits Truckee and the Sierra, starts here.

ReadingMountain preset
Max wind25 mph
Max rain chance50 percent
Max total precipitation0.5 inch
Min temperature25 F
Max temperature89 F
Snow flag2 inches

These are starting points, not safety rules. Your company policy, the equipment manufacturer and OSHA or Cal/OSHA requirements come first.

When the call is NO-GO

The crew limits above decide CAUTION. NO-GO is only for weather that truly stops outdoor work, judged over the 7 AM to 7 PM work day (today, the hours still ahead).

WeatherNO-GO line
Heavy snow8 inches of snow or more in the work hours
Heavy rain1 inch of rain or more in the work hours
Damaging windGusts of 50 mph or more, or sustained wind of 35 mph or more
Dangerous coldA work hour at 0 F or colder, or a wind chill of -15 F or colder
Ice storm0.10 inch of freezing rain or more
ThunderstormsA 60 percent thunderstorm chance, or a storm active now under a warning
Extreme heatA high or feels like of 105 F or more
SmokeHazardous air, AQI 301 or more (AQI 151 and up is CAUTION under the Cal/OSHA wildfire smoke rule)
NWS warningsBlizzard, Ice Storm, Flash Flood, High Wind, Extreme Cold, Tornado, Severe Thunderstorm, Hurricane or Tropical Storm Warning, an evacuation order or a Fire Warning

A 7 F morning, 3 inches of snow, a half inch of rain, 40 mph gusts, a Winter Storm Warning or a Wind Advisory is CAUTION: plan around it. Lightning is always a stop when you hear thunder, whatever the forecast said.

How the tool makes the call

It blends eight weather models, layers the HRRR over the first 18 hours, and checks the result against your limits for each hour and each day. The Kerr Blend is graded every day against the Truckee airport station, and the error is published openly on the forecast accuracy tab. For Truckee and the Sierra, see the Truckee weather forecast and the Kerr Storm Tracker, errolkerr.com's own future radar.

Questions

What does GO, CAUTION and NO-GO mean for a construction crew?

GO means conditions are inside the crew's limits and work proceeds as planned. CAUTION means one or more readings are close to a limit, so the foreman adjusts the plan, shortens exposure or moves the risky task. NO-GO is saved for weather that truly stops outdoor work during the 7 AM to 7 PM work day: 8 inches of snow or more, 1 inch of rain or more, gusts of 50 mph or sustained wind of 35 mph, a work hour at 0 F or colder or a wind chill of -15 F, 0.10 inch of freezing rain, a 60 percent thunderstorm chance, 105 F heat, or a stop-work NWS warning such as a Blizzard, Ice Storm, Flash Flood or High Wind Warning. Everything short of that, including a Winter Storm Warning, is CAUTION.

What weather limits should a foreman use to stop work?

Common limits are sustained wind and gusts, rain chance and total rain, lightning within a set distance, high and low temperature, and snowfall. The Crew Weather tool starts from a preset for the jobsite's climate zone. For mountain jobsites the preset is wind 25 mph, rain chance 50 percent, 0.5 inch total precipitation, a low of 25 F, a high of 89 F and 2 inches of snow. Crews can change every number, and company policy, the equipment manufacturer and OSHA or Cal/OSHA rules come first.

How does the Crew Weather tool make the call?

It blends eight weather models, layers the HRRR over the first 18 hours, and compares the result to the crew's thresholds for each day and hour. The Kerr Blend is checked daily against the Truckee airport station, and the published error is at errolkerr.com/accuracy.

Is the Crew Weather GO/NO-GO tool free?

Yes. errolkerr.com/crew-weather is free, needs no signup and works for any US location by ZIP code.

Does the tool replace the foreman's judgment?

No. It is a decision aid. The foreman on site, the safety plan and the applicable regulations make the final call. Lightning in particular is a stop-work event: when thunder is heard, go to shelter and follow your site lightning procedure.

This is Errol's own forecast guidance. It does not replace the National Weather Service or Caltrans QuickMap road conditions. Avalanche danger comes from the Sierra Avalanche Center; lift and terrain status comes from the resort.